Document: Water Connection Permit
Agency: City of Hermiston Water Department
Contact: Pat Napolitano, Water Superintendent
541-567-5521
180 N.E. 2nd Street, Hermiston, OR 97838
Process: There is no formal application process, but a connection permit must be purchased prior to obtaining a building permit.
Procedure: Not applicable
Timeline: Water connection permits can generally be obtained in less than a day.
Fee: Established by city council resolution. Connection fees and system development charges are assessed based upon the size of the water meter. Connection fees range from $900 for a 3/4-inch meter to $5,800 for a 4-inch meter. SDCs range from $504 for a 3/4-inch meter to $12,600 for a 4-inch meter.