| Document: |
Water Connection Permit |
| Agency: |
City of Hermiston Water Department |
| Contact: |
Pat Napolitano, Water Superintendent 541-567-5521 180 N.E. 2nd Street, Hermiston, OR 97838 |
| Process: |
There is no formal application process, but a connection permit must be purchased prior to obtaining a building permit. |
| Procedure: |
Not applicable |
| Timeline: |
Water connection permits can generally be obtained in less than a day. |
| Fee: |
Established by city council resolution. Connection fees and system development charges are assessed based upon the size of the water meter. Connection fees range from $900 for a 3/4-inch meter to $5,800 for a 4-inch meter. SDCs range from $504 for a 3/4-inch meter to $12,600 for a 4-inch meter. |